Sinohydro, China International Among Three Firms Qualifying for Sunkoshi Marin Construction Contract

Three bidders have passed the technical evaluation for the remaining civil and hydromechanical works after the previous Rs 14.08 billion contract was terminated over poor progress. The fresh tender follows a Supreme Court ruling that cleared the way for the government to seize Rs 3.6 billion in bank guarantees

An aerial view of the Sunkoshi Marin Diversion Multipurpose Project. RSS File

Three bidders, including Chinese construction companies Sinohydro Corporation Limited and China International Water and Electric Corporation, have cleared the technical evaluation for a contract to complete the remaining civil and hydromechanical works of the Sunkoshi Marin Diversion Multipurpose Project.

According to a notice issued by the project office on Tuesday, October 13, China International Water and Electric Corporation, Anneng RCC Joint Venture (JV) and Sinohydro Corporation Limited have qualified for the next stage of the procurement process.

Sinohydro has been involved in the construction of several major hydropower projects in Nepal, including Upper Tamakoshi, Tanahu Hydropower and Tamakoshi V. China International Water and Electric Corporation has also undertaken hydropower and irrigation projects in the country.

The project office has invited the three qualified bidders to attend the opening of their financial proposals at 1 pm on November 2, 2026, at its office in Sindhuli.

The financial bids will be evaluated before the authorities proceed with the remaining procedures for awarding the contract.

The fresh procurement process follows the termination of an earlier contract awarded to Patel Raman JV for approximately Rs 14.08 billion. The contract covered the construction of the dam, powerhouse and other civil structures, along with the supply and installation of gates and other hydromechanical equipment.

The project authorities initiated termination proceedings after physical progress remained at around 10%, despite approximately 61% of the contract period having elapsed.

According to the project authorities, the contractor failed to achieve the required progress despite repeated instructions to accelerate construction.

On November 11, 2025, the project office decided to terminate the contract and issued a notice giving the contractor 15 days to respond. It also initiated proceedings to seize bank guarantees totalling Rs 3.6 billion, comprising Rs 2.4 billion in performance guarantees and Rs 1.2 billion in advance payment guarantees.

Patel Raman JV challenged the decision in the Supreme Court, filing a writ petition on November 25 against the project office, the Ministry of Energy, Water Resources and Irrigation, and other concerned authorities.

On November 26, a Supreme Court bench led by Justice Tek Prasad Dhungana issued a temporary interim order preventing the authorities from implementing the contract termination and seizing the bank guarantees. The court also summoned both parties for hearings.

The government subsequently sought to have the interim order vacated.

On February 10, 2026, a division bench comprising Justices Hari Prasad Phuyal and Nityananda Pandey ruled that the earlier interim order would not continue, removing the legal restriction that had temporarily prevented the authorities from proceeding with the termination and guarantee seizure.

The ruling cleared the way for the government to pursue the seizure of the contractor's performance and advance payment guarantees, worth a combined Rs 3.6 billion.

Following the termination, the project authorities assessed the work already completed, equipment available at the construction site, outstanding construction activities and additional structures required. The assessment formed the basis for preparing revised cost estimates and fresh bidding documents.

The government subsequently invited international competitive bids on June 8, 2026, for the remaining construction works.

The Sunkoshi Marin Diversion Multipurpose Project is designed to divert water from the Sunkoshi River to the Marin River through a tunnel, providing irrigation to agricultural land in the Terai while generating 31 MW of electricity.

With three bidders now through to the financial evaluation stage, the project has moved closer to selecting a new contractor for the remaining construction works.