“We have been asked to fast-track the project under laws dating back to the 1950s. If these laws are not updated in time, I cannot assure completion by 2027,” then Nepali Army Chief Prabhu Ram Sharma told the State Affairs and Good Governance Committee of the House of Representatives on December 21, 2023, while presenting a progress report on the Kathmandu–Tarai Expressway.
He warned that the 2027 deadline would be impossible without revising the Forest Act and the Land Acquisition Act.
Sharma said it can take up to nine months just to secure approval to cut four trees at the project site. He also flagged major hurdles in land acquisition. “Landowners are demanding far more than what the government is willing to pay. Acquiring private land has been a huge challenge, and this is another key reason for the delay,” he said.
The Kathmandu–Tarai Expressway is one of the government’s flagship projects. But progress has been slow, even with the Nepali Army leading construction. Like many publicly funded infrastructure projects, it is running behind schedule. Work began in August 2017 with a four-year deadline. As delays mounted, the government extended the timeline to August 2021, and then to December 2024. With that timeline also proving unrealistic, the completion date has now been pushed to April 2027.
The 70.97-kilometer project is a clear example of how infrastructure is managed in the country. Outdated laws, complex procurement rules, and weak project preparation continue to slow infrastructure projects. These systemic bottlenecks in project implementation are visible across the country.
Construction of the Koshi Corridor road project began in FY 2008/09. The 162-km road runs from Basantapur in Terhathum to Kimathanka on the Nepal-China border. Originally scheduled for completion in 2023/24, the timeline has now been extended to 2028/29. Progress stands at just 46% and costs have risen from Rs 11.93 billion to Rs 16.20 billion, with Rs 6.85 billion already spent.
Work on the Kaligandaki Corridor also remains incomplete. The 495-km road connects Gaindakot on the East-West Highway to Maldhunga of Parbat and extends along the Beni–Jomsom to Korala on the Nepal-China border. So far, 87 km is graveled and 328 km blacktopped. However, contracts are still pending for 40.42 km of blacktopping and 22 bridges. Overall progress of the project stands at 82.05%.
The Karnali Corridor shows even slower progress. Since construction began in 2008/09, physical progress has reached just 20.5%. The deadline, originally set for 2013, has now been pushed to 2027/28. Costs have surged from Rs 4.10 billion to Rs 18.66 billion. The Mid-Hill Highway, one of Nepal’s largest infrastructure projects, has been under construction for nearly two decades. It is still incomplete, with progress at 84.69%. Of the planned 1,879 km, 1,067.6 km has been blacktopped and 114 bridges built. Costs have jumped from Rs 33.36 billion to Rs 84.33 billion, with Rs 71.91 billion already spent. Even here, new contracts have been stalled due to a lack of resource approval.
A similar situation exists in the Madan Bhandari Highway Project. No new contracts have been awarded this fiscal year. Work is limited to older contracts, even as the liabilities stand at around Rs 14 billion against an allocation of just Rs 2.50 billion.
Nepal does not lack ambition. Roads, transmission lines, irrigation systems, airports, and urban projects are announced every year. The challenge lies in execution. The gap between allocation and completed projects has become a serious constraint on economic growth. A recent World Bank report, Nepal Capital Expenditure Bottlenecks Analysis, finds that persistently low execution of infrastructure spending has limited the buildup of public capital, creating major barriers to economic growth. The problems begin early. Projects often enter the budget without proper appraisal, realistic costing, or clear timelines. Procurement processes are slow and rigid. The system relies heavily on the lowest bidder, often at the expense of quality. Monitoring is weak, with little real-time data to track progress or resolve bottlenecks. Structural constraints add to the problem. Land acquisition disputes, lengthy environmental and tree-cutting approvals, and weak cash management all affect project implementation. Budget reallocations and gaps in procurement rules create further uncertainty. These challenges are interconnected and reinforce each other across the project cycle.
The Promise and the Paradox
Few countries need infrastructure as urgently as Nepal. Its geography makes connectivity costly and complex. Poor transport raises trade costs, weak transmission systems limit hydropower use, and inadequate urban systems constrains productivity.
To further aggravate the situation, the country’s public capital base has been eroding. Public capital stock, once estimated at around 75% of GDP in the mid-1990s, fell to about 54% by 2019. Spending has been inconsistent. Between 2005 and 2015, capital spending averaged just 2.7% of GDP. This is well below what comparable economies were investing. After the 2015 earthquakes and the shift to federalism, public investment rose sharply, peaking at 11.4% of GDP in 2021. But the momentum did not last. According to Rabi Singh, former president of the Federation of Contractors' Association of Nepal, Nepal’s weak capital expenditure is not just a budgeting issue; it directly translates into stalled, delayed, and poorly executed projects. “Low and uneven capital spending means projects do not get money when they actually need it. Although budgets are announced at the start of the fiscal year, funds are often released late or in small tranches,” he added.
Because of this, contractors cannot mobilize equipment, labor, or materials on time. Many projects only begin meaningful work in the final quarter of the fiscal year, compressing what should be a year-long construction cycle into just a few months. This leads to rushed work, compromised quality, and incomplete infrastructure.
By 2023/2024, capital expenditure had dropped back to 7.9% of GDP. At the same time, total capital allocations across federal, provincial, and local governments fell from around 20% of GDP to 12% between 2019/2020 to 2023/2024.
Even allocated funds are not fully spent. Between 2020/2021 and 2023/2024, under execution reduced public investment by about 5% of GDP on average.
For a country that needs to invest 10-15% of GDP over the current decade to close its infrastructure gap, that shortfall is quite significant. Another major impact is the stop–and–go nature of projects. When capital expenditure remains low, like the roughly 19% spending by mid-year, contractors face cash flow problems because payments are delayed. This slows progress, and in some cases leads to contractors abandoning sites altogether. Smaller contractors are especially vulnerable, as they lack the financial buffer to sustain long delays in government payments.
Too many projects, too little discipline
The breakdown in the capital spending system begins well before construction. In theory, projects are supposed to pass appraisal before they enter the budget. The National Project Bank was created to ensure that only well-prepared and prioritized projects receive funding. In practice, it does not.

Projects continue to enter the Medium-Term Expenditure Framework and annual budgets without passing a credible prioritization process. Many lack proper feasibility studies, realistic cost estimates, or clear timelines. Instead of focusing resources on a manageable number of high-priority projects, funding is spread thinly across too many projects. The result is over commitment.
According to Singh, when projects are chosen for political appeal, they are typically driven by short-term incentives: winning votes, satisfying local constituencies, or showcasing visible “development” before elections. “This means leaders may prioritize projects that are highly visible, like roads in specific districts or symbolic infrastructure, rather than those that are technically sound or economically necessary,” he added.
Data from a subset of major projects illustrates the scale of the problem. For 17 ongoing national pride projects, the allocation provided in the 2023/2024 budget implies a completion timeline of 41 years. Even if the entire federal capital budget were directed exclusively toward those projects, it would still take eight years to complete them.
This problem is visible in large transport projects as well. When funding is spread thinly across multiple packages and years, projects such as the East–West Highway expansion struggle to maintain momentum across all sections, leading to uneven and prolonged implementation. This is not a financing problem alone. It is a planning problem. Too many projects are approved without a clear understanding of what it will take to finish them.
According to experts, ignoring economic return further weakens outcomes. Ideally, capital expenditure should go into projects that generate productivity, like transport corridors, irrigation systems, or energy infrastructure that boost industry and agriculture. “But politically motivated projects may not deliver sufficient returns, meaning public money is spent without significantly improving growth or livelihoods,” Singh said.
This also leads to budget fragmentation. To satisfy multiple political interests, many small projects are included in the budget rather than focusing on a few well-prepared, high-impact ones. Each project then receives limited funding which slows progress across the board and leads to a proliferation of incomplete works.
Delayed Before Work Begins
Even when projects are approved and budgeted, many are not ready to begin. Two bottlenecks dominate the early stages of project implementation: forest clearance and land acquisition. Securing permission to cut trees for infrastructure projects typically takes between 22 and 24 months. The process involves multiple layers of approval across ministries, provincial authorities, forest offices, and the Cabinet.
A key source of delay is the requirement for a manual tree census conducted by district forest offices. This process alone can take around 10 months. If the census results differ significantly from the original environmental impact assessment, authorities may require a supplementary assessment, effectively restarting the process.
The system is not only slow. It is circular. Projects that have already been appraised and approved can find themselves repeating core steps due to discrepancies and procedural gaps. Digital tools that could speed up surveys are rarely used.
According to Singh, tree-cutting permissions have remained a chronic bottleneck across high-value public works in Nepal for a long time. “It has significantly delayed project implementation. Multiple projects are held up for months because environmental clearances take far too long, creating a stop–start pattern in construction that inflates costs and reduces efficiency,” he added. Singh adds that despite repeated discussions and calls for reform over the years, the government has yet to take proactive measures to streamline approval processes or improve coordination across agencies. The delays stem from a combination of institutional and legal weaknesses. Nepal’s land information systems are incomplete and not fully integrated. Different agencies use different valuation methods. Official valuations often fall below market prices, leading to disputes over compensation.
The legal framework itself is outdated. The Land Acquisition Act, which dates back to 1977, does not adequately address modern infrastructure needs or the realities of informal land use. Disputes are common, and litigation can stall projects for years. Together, these bottlenecks mean that many projects enter the budget without being truly ready.
Weak Cash Management
Even projects that clear early hurdles face challenges during implementation. One of the most persistent features of Nepal’s capital spending is the concentration of expenditure in the final months of the fiscal year. This pattern is partly driven by delays in project readiness and procurement. But it is also a result of how cash is managed. Although spending units are formally authorized to use their full annual budget once it is approved, funds are effectively released every quarter. When revenue falls short of expectations, as it has in recent years, the government often resorts to cash rationing. This creates uncertainty for implementing agencies and contractors. Projects that are ready to move may face delays simply because funds are not available at the right time.
According to Devendra Karki, a former government secretary, the major challenge is payment issues. “Funds are often released in small, fragmented tranches rather than in sufficient amounts to sustain work. Contractors cannot mobilize labor, machinery, or materials efficiently under these conditions. This results in slow progress and increased costs,” he added. Foreign-funded projects face an additional layer of complexity. Reimbursement-based financing arrangements mean that funds for later quarters may depend on spending in earlier ones. When domestic co-financing falls short or reporting is delayed, fund releases can be held back which creates a cycle of low execution. The result is a system where money arrives late and must be spent quickly, often at the expense of efficiency and quality.
Procurement: The Final Choke Point
Procurement remains another major hurdle. Procurement data from World Bank systems show that Nepal has the longest average contract processing time in South Asia. According to the World Bank’s Systematic Tracking of Exchanges in Procurement (STEP), the government took an average of 231 business days to complete various stages of procurement for contracts awarded between 2018 and 2024. This is well above the South Asia average of 192 days.
A business process review of 19 largest active World Bank-funded contracts in Nepal found average delays of 89 business days for consultancy contracts and 110 business days for works contracts. Among consultancy contracts, the main bottleneck was the preparation of the bidder shortlist and Request for Proposals, with delays of around 100 business days beyond planned timelines. For works contracts, delays were driven largely by time overruns in preparing pre-qualification evaluation reports and drafting bidding documents. The reasons are both procedural and structural.
Procurement decisions often pass through multiple layers of approval, even for relatively small contracts. Project implementation units have limited authority, and key decisions must be escalated up the hierarchy. Paper based processes and the absence of standardized workflows add further delays. The regulatory framework also creates perverse incentives. Contracts are typically awarded to the lowest evaluated bidder, with limited scope to reject bids that are unrealistically low. This can lead to poor quality work or cost overruns later.
At the same time, strict penalties for contract termination make it difficult to manage underperforming contractors, often leading to prolonged disputes. These dynamics are visible in large scale road projects. The East–West Highway upgrade works, spread across multiple packages, have faced delays linked to procurement processes and contract execution challenges.
When Approvals Stall, Everything Stalls
Construction of national pride and strategically important projects is now at risk of being delayed by at least a year, as the government has yet to grant multi-year resource approval. Although the Ministry of Finance introduced the Multi-Year Project Resource Agreement Criteria in mid-December, it has not been implemented. As a result, new contracts for major projects cannot be awarded in the current fiscal year, according to project officials.

This has affected several road projects, including the Koshi, Kaligandaki, and Karnali corridors, as well as the Mid-Hill Highway and other strategic networks. Under the guidelines, agencies were required to submit proposals to the National Planning Commission (NPC) by mid-December. The NPC was expected to complete its review by mid-January and forward recommendations to the Ministry of Finance for a final decision by the end of January. However, no decision has been made so far. The delay has created uncertainty across major infrastructure projects. Even where proposals were submitted on time, the lack of approval has stalled procurement. This has prevented new contracts and slowed progress. Officials say no new work can begin without resource approval. Ongoing work under existing contracts can continue, but if approval is not granted within the current fiscal year, the procurement cycle will shift to the next year, pushing timelines further out, they say.
The process was further slowed by the election code of conduct, which limited administrative decisions, enforced for the March 5 elections.
According to Karki, a major hurdle in Nepal’s infrastructure development is the lack of clear ownership and coordination of government projects. Currently, many projects are treated as belonging solely to individual departments—for example, road projects are often managed only by the Department of Roads, while forest or environmental issues are handled separately. Similarly, the Ministry of Finance controls budget approvals independently, creating situations where funds are delayed or not released on time.
“Without a coordinated approach, projects will suffer as there is no collective accountability or support. For infrastructure projects to progress effectively, all relevant government bodies must take joint ownership of major projects, working together to provide approvals, technical guidance, and financial support,” said Karki.
The Ministry of Finance says it is committed to speeding up implementation through multi-year budgeting. But the current delays point to deeper structural weaknesses in how projects are approved and executed.
Can Nepal Learn to Finish What it Starts?
Fixing capital expenditure problems will require more than incremental reforms. It will require a shift in how the state approaches public investment. The issue is no longer how much Nepal budgets for infrastructure, but whether it can build what it budgets.
The first step is discipline at entry. Projects should not enter the budget without a credible appraisal, realistic costing, and a clear financing path. The second is visibility. A reliable, integrated system that tracks project costs, timelines, and progress is essential for effective planning and monitoring. The third is prioritization. The current portfolio is too large and too fragmented. Rationalizing projects and focusing resources on those that matter most will be critical.
At the same time, key procedural bottlenecks must be addressed. Forest clearance and land acquisition processes need to be streamlined and modernized. Cash management practices must be aligned with project needs, not just revenue flows. Procurement rules should balance efficiency with quality, allowing for better judgment in contractor selection.
None of these reforms is simple. But without them, the gap between ambition and execution will persist. Nepal does not lack plans. It does not lack projects. What it lacks is a system that can consistently take projects from paper to completion. Until that changes, the country’s infrastructure gap will remain not just a development challenge, but a structural brake on growth.
According to Karki, issues arise from mismatches between contractor capacity and project size. “Some contractors take on projects larger than their equipment, workforce, or technical expertise can handle. In many cases, critical machinery is limited to one location while projects are spread across multiple sites. This forces delays or inefficient work practices,” he said. “Until these issues are addressed, Nepal’s infrastructure development will continue to face chronic hurdles and even well-funded projects with approved plans can be delayed for years.
This report was originally published in April 2026 issue of New Business Age magazine.
you need to login before leave a comment
Write a Comment
Comments
No comments yet.